But FERC put the brakes on Amazon’s expansion plan, voting 2-1 against Talen’s (TLN) request, saying that the plan didn’t ...
The US Federal Energy Regulatory Commission (FERC) has rejected a proposal that would have allowed an Amazon data centre ...
The commission agreed with opponents of the proposal, citing concerns about grid reliability and cost fairness.
Discover if Talen Energy (TLN) remains a buy after FERC's Amazon deal block. Analyze key price levels and future prospects.
The Federal Energy Regulatory Commission (FERC) stopped an Amazon AI data center from drawing more power from Talen Energy’s Susquehanna plant in Pennsylvania.
FERC rejected an interconnection service plan proposed to raise the load capacity of an Amazon data centre at Susquehanna ...
Nuclear plant owner Talen Energy Corp. says an initial 300 MW of data center development can proceed despite feds' rejection of grid link agreement to its Susquehanna facility in Pennsylvania's ...
Amazon.com Inc. said it’s committed to building a data center campus adjacent to a Pennsylvania nuclear plant after the top ...
The Amazon data center is located close to Talen's Susquehanna nuclear power plant in Pennsylvania, as previously reported. The amended interconnection deal would have supplied more power directly ...
The Federal Energy Regulatory Commission (FERC) has rejected an amended interconnection agreement that would have supported ...
The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to tap into ...
The company’s “foot is on the accelerator” to close data center deals as it works to restart Three Mile Island Unit 1 by 2027 ...